top of page

SOLUTION 5

Total savings over 5 years

Total cost over 5 years

Required equipment

Diagram Solution 5 (C (a)).png

3''

5

3     4

6     3'

Preexisting 

heat exchanger

Heat exchanger (3-4)

We first calculate the heat gained by the system with the heaters in the plant using the formula:

​

 

We then calculate the temperature difference to plug into the equation 

​

 

We find that 

 

​

​

We first calculate the heat gained by the system with the heaters in the plant using the formula:

​

 

We then calculate the temperature difference to plug into the equation 

​

 

We find that 

 

​

​

Stream 3

Heat capacity*Mass flowrate

40.3 kW/°C

Heat gained by system

-2700.1 kJ/s

Temperature in

107°C

Temperature out

40°C

We first calculate the heat gained by the system with the heaters in the plant using the formula:

​

​

We then calculate the temperature difference to plug into the equation

​

 

We find that 

​

​

​

render.png
Stream 3.png
Streaam 3.png

We first calculate the heat gained by the system with the heaters in the plant using the formula:

​

 

We then calculate the temperature difference to plug into the equation 

​

 

We find that 

 

​

​

We first calculate the heat gained by the system with the heaters in the plant using the formula:

​

 

We then calculate the temperature difference to plug into the equation 

​

 

We find that 

 

​

​

Stream 4

Heat capacity*Mass flowrate

2.2 kW/°C

Heat gained by system

129.8 kJ/s

Temperature in

40°C

Temperature out

99°C

We first calculate the heat gained by the system with the heaters in the plant using the formula:

​

​

We then calculate the temperature difference to plug into the equation

​

 

We find that 

​

​

​

render.png
Stream 4.png
Stream 4.png

We first calculate the heat gained by the system with the heaters in the plant using the formula:

​

 

We then calculate the temperature difference to plug into the equation 

​

 

We find that 

 

​

​

Heat exchanger

Remaining heat 

2570.3 kJ/s

Temperature Hot out

103.78°C

Log mean Temperature 

26.89°C

We now seek to find the maximum amount of heat that can be exchanged between stream 3 and stream 4. This maximal amount corresponds to the lowest value of the absolute value of heat gained by the system between stream 3 and 4. 

​

​

From that we calculate the remaining heat that needs to be removed

​

​

 

And the effective temperature out of Stream 3 

​

​

 

Finally, we calculate the log mean temperature using the formula 

render.png
3,4.png
26.89.png
3,4.png
2570.3.png
render.png

Cost

Cross sectional area 

5.62m²

Costs

5 633£

Variance on cost

±845£

We first calculate the area required for the heat exchanger based on this equation:

​

​

where U represents the overall heat transfer coefficient

and Q represents the actual amount of heat tranferred between the two streams above.

 

We then calculate the cost using the following formula:

%

Formula for cost .png
Overall formula for areea.png
3,4.png
3,4.png
Heat exchanger (3-4)

Heat exchanger (3'-6)

Stream 3'

Heat capacity*Mass flowrate

40.3 kW/°C

Heat gained by system

-2570.3 kJ/s

Temperature in

103.78°C

Temperature out

40°C

render.png

We first calculate the heat gained by the system with the heaters in the plant using the formula:

​

 

We then calculate the temperature difference to plug into the equation 

​

 

We find that 

 

​

​

Q dot 3'.png
3'.png

Stream 6

Latent heat of vaporisation

2000 kJ/kg

In stream 6, the substance goes through a phase change whilst remaining at 94°C. We thus use the formula: 

​

​

 

We know that the massflowrate is 12kg/s. Additionally, we know that the specific latent heat of vaporisation is 2000kJ/kg. 

​

We thus plug in the numbers and find that

​

​

 

​

​

Heat gained by system

240 kJ/s

Mass flowrate

0.12 kg/s

render.png
render.png

 

Phase Change

We first calculate the heat gained by the system with the heaters in the plant using the formula:

​

 

We then calculate the temperature difference to plug into the equation 

​

 

We find that 

 

​

​

Heat exchanger

Remaining heat 

2330.3 kJ/s

Temperature Hot out

97.82°C

Log mean Temperature 

6.34°C

We now seek to find the maximum amount of heat that can be exchanged between stream 3' and stream 4. This maximal amount corresponds to the lowest value of the absolute value of heat gained by the system between stream 3' and 4. 

​

​

From that we calculate the remaining heat that needs to be removed

​

​

 

And the effective temperature out of Stream 3' which we find to be equal to 97.82 degrees celcius. 

 

Finally, we calculate the log mean temperature using the formula 

6.34.png
2330.3.png
Q3'6.png

Cost

Cross sectional area 

44m²

Costs

19 370£

Variance on cost

±2 905£

We first calculate the area required for the heat exchanger based on this equation:

​

​

where U represents the overall heat transfer coefficient

and Q represents the actual amount of heat tranferred between the two streams above.

 

We then calculate the cost using the following formula:

render.png

%

Overall formula for areea.png
3',6.png
3'6.png
Formula for cost .png
Heat exchanger 3'-6

Heat exchanger (3''-5)

Stream 3''

Heat capacity*Mass flowrate

40.3 kW/°C

Heat gained by system

-2330.3 kJ/s

Temperature in

97.82°C

Temperature out

40°C

render.png

We first calculate the heat gained by the system with the heaters in the plant using the formula:

​

 

We then calculate the temperature difference to plug into the equation 

​

 

We find that 

 

​

​

3''.png
Q dot 3''.png

We first calculate the heat gained by the system with the heaters in the plant using the formula:

​

 

We then calculate the temperature difference to plug into the equation 

​

 

We find that 

 

​

​

We first calculate the heat gained by the system with the heaters in the plant using the formula:

​

 

We then calculate the temperature difference to plug into the equation 

​

 

We find that 

 

​

​

Stream 5

Heat capacity*Mass flowrate

38.1 kW/°C

Heat gained by system

1181.1 kJ/s

Temperature in

40°C

Temperature out

71°C

We first calculate the heat gained by the system with the heaters in the plant using the formula:

​

​

We then calculate the temperature difference to plug into the equation

​

 

We find that 

​

​

​

render.png
Streqm 5.png
Stream 5.png

We first calculate the heat gained by the system with the heaters in the plant using the formula:

​

 

We then calculate the temperature difference to plug into the equation 

​

 

We find that 

 

​

​

Heat exchanger

Remaining heat 

1149.2 kJ/s

Temperature Hot out

68.52°C

Log mean Temperature 

27.66°C

We now seek to find the maximum amount of heat that can be exchanged between stream 3'' and stream 5. This maximal amount corresponds to the lowest value of the absolute value of heat gained by the system between stream 3'' and 5. 

​

​

From that we calculate the remaining heat that needs to be removed

​

​

 

And the effective temperature out of Stream 3'' is found to be 97.82 degrees celcius, using the same formula as previously stated 

​

Finally, we calculate the log mean temperature using the formula and find

1149.2.png
27.66.png
Q3''5.png

Cost

Cross sectional area 

49.6m²

Costs

20 825£

Variance on cost

±3 124£

We first calculate the area required for the heat exchanger based on this equation:

​

​

where U represents the overall heat transfer coefficient

and Q represents the actual amount of heat tranferred between the two streams above.

 

We then calculate the cost using the following formula:

render.png

%

Overall formula for areea.png
Formula for cost .png
3''5.png
3'',5.png
Heat exchanger 3''-5

Overall cost

Money saved

723 400 ±6 800£

New total cost

527 000 ±6 800£

Utility cost (per year)

96 000£

Installation cost

45 800 ±6 800£

%

The total cost for this solution is the sum of the costs for utility over 5 years and the installation of the 3 heat exchangers.

Utility costs arise from the requirement for further heating or cooling once a stream has passed through a heat exchanger. If no exchanger is installed on a stream, utility costs for that flow will remain unchanged.

​

Cooling in this case (requires 2 coolers):

  • The temperature of Stream 2 needs to be reduced by 54.00 °C

  • The temperature of Stream 3 needs to be reduced by 28.52 °C

​

Heating in this case (requires 1 heater):

  • The temperature of Stream 1 needs to be raised by 41 °C

​

This gives rise to a total utility cost over 5 years of £481,000.

Year 1 Costs Solution 5 (C (a)).png
5 Year Costs Solution 5 (C (a)).png
Overall cost
bottom of page